Step 1: Land Verification
- Cost: UGX 50,000-150,000 for search at DLB
- Check: Zoning (residential/commercial) and encumbrances
|  | 
| Building Permits in Uganda: The 2024 Step-by-Step Guide | 
Step 2: Submit Plans
- Who Approves: KCCA (Kampala) or District Physical Planners
- 4x architectural drawings
- Structural engineer’s report
- EIA certificate (for buildings >8 floors)
Kampala Rates:
- Residential: 0.5% of project value
- Commercial: 1% (min. UGX 200,000)
- Timeline: 14-21 days after submission
- Critical: Be present during KCCA site visits
- Starting construction before approval (3x penalty fees)
- Using uncertified architects (plan rejection risk)
- Pro Tip: "Approvals take 30% less time in Wakiso vs. Kampala"
Need Help? Find licensed architects on our platform Here
 
 
 